City Centre Construction Update 5 July 2024

Welcome to the weekly e-newsletter for the Bradford City Centre Walking and Cycling Improvements Scheme.

This edition includes everything you need to know about the Bradford City Centre Walking and Cycling Improvements Scheme for the coming days. We upload each weekly newsletter to the Future Bradford website. You can find copies of each e-newsletter on our news page if you would like to look back at previous editions. 


Watch: Bradford BID’s guide on getting around the city centre

Bradford Business Improvement District (BID) is working on behalf of local businesses to deliver key investments and economic growth for Bradford city centre.

Bradford BID have produced a handy video that explains where the nearest buses, taxis, and car parking can be found during the construction phase of Bradford city centre’s transformation.

A link to the Blue Badge parking map can be found here.

A link to the taxi rank map can be found here.

You can view the Bradford city centre bus stop map by clicking here.

To find out more about the Bradford BID, and the work they do in our city click here.

Watch Bradford BIDs guide on getting around the city centre by clicking on the video above, or on their Facebook page by clicking here.


New planters and paving in city centre 

Works are continuing to progress well in the city centre. More new paving has been laid down on much of Market Street, which will also see new planting and greenery added.

On Bank Street more paving has been laid between Market Street and Broadway. and new bollards near to the junction with Hall Ings are continuing to be installed.

This week, we have been preparing to install planting areas on Broadway at the junction with Bank Street. These planters will feature a mix of flowers, plants and grass.

On Bridge Street new paving for the future service vehicle route continues to be laid on the City Park side of the road. A large planter area will also be installed in this area, which will include an array of tree species.

Images showing progress of works in the city centre, of three planters.


Works started on West Bradford Cycle Superhighway Extension

Work to expand the existing Bradford Leeds Cycle Superhighway to connect to West Bradford is progressing well.

Over the next few weeks, we will be surfacing the north side footpath on Sunbridge Road, and new cycleway on Sunbridge Road between Barry Street and Wigan Street.

Pedestrians will be diverted to the south side of Sunbridge Road while this work is being carried out. Parking will soon be suspended on Sunbridge Road between Barry Street and Wigan Street, and will not be reinstated once the work is complete, as this section of Sunbridge Road will see a new cycle lane in place.

Further details about the scheme and upcoming works are available on the Future Bradford website, updates of the works will also be shared in future e-newsletters.


Overnight works now complete

Overnight works on Sunbridge Road, Godwin Street, Prince’s Way and Manchester Road are now complete. The works have seen new road surfacing and markings.

We’d like to thank residents and businesses for their cooperation and understanding during periods of night working.


Reminder: No right turn from Croft Street to Manchester Road

It is not possible to make a right turn from Croft Street to Manchester Road.

This change came into effect earlier this year as part of new traffic management measures resulting from the transformation works in the city centre.

It is important that drivers take note of the signage and road layout changes as they are in place for everyone’s safety.

More signage has been placed to remind drivers of the new layout. 

Image of a sign in place at Croft Street that reads ‘no right turn onto Manchester Road’. 


Reminder: Temporary pedestrian crossings

Temporary pedestrian crossings have been opened up across the city centre in places where works are happening.

We have included a map of the pedestrian crossing points in the core of the city centre below.

Map showing the pedestrian crossing points in the city centre. Crossings are in place at the following locations: Market Street, at the junctions with Charles Street, Bank Street and Bridge Street, as well as on Hall Ings at the junction with Bank Street.



Reminder: temporary closure of the Bradford Interchange bus station 

Information about alternative bus stops for services unable to use the Interchange Bus Station can be found on the Metro website. You can read the Combined Authority's latest update on the closure of the Bradford Interchange Bus Station on their website


Find out more

You can find out more about the scheme on the Future Bradford website or by getting in touch using the details and links below. 

Get in touch if you would like to ask any questions

Email:info@future-bradford.co.uk

Write: Freepost BFD Highways

X (formerly Twitter):@bmdcHighways

Instagram:bradfordhighways

Facebook:Bradford Council Highways


 
 

Other news that might interest you


Previous
Previous

City Centre Construction Update 12 July 2024

Next
Next

City Centre Construction Update 28 June 2024