City Centre Construction Update 23 August 2024

An image showing the progress of green paving that has been laid down on Sunbridge Road for the new cycleway.

Welcome to the weekly e-newsletter for the Bradford City Centre Walking and Cycling Improvements Scheme.

This edition includes everything you need to know about the Bradford City Centre Walking and Cycling Improvements Scheme for the coming days. We upload each weekly newsletter to the Future Bradford website. You can find copies of each e-newsletter on our news page if you would like to look back at previous editions. 


This weeks city centre progress

Good progress has been made with surfacing works in the Sunbridge Road area, where a new cycleway is being constructed. The new cycle lane has had it’s green surfacing laid down in recent weeks and is now fully visible. In the coming weeks, we will be adding the finishing touches including adding the white cycle marking along the lane.

Ultimately, these cycleways will connect with the new Cycle Superhighway works west of the city on Sunbridge Road and Thornton Road, which are currently under construction

We have shared some images below of the progress that has been at Sunbridge Road.

Across all parts of the city centre where works are happening, paving works are continuing, alongside installation of new raised planter units. Specifically, new paving is progressing along Bridge Street towards the Sunbridge Road junction, and at the Market Street and Bank Street junction, raised planter wall units have been installed.

You can find out more about the works happening in this area by visiting Future Bradford website.

Two images showing new paving and planter units being installed. From top to bottom: A new raised planter unit installed at the Market Street and Bank Street junction; and new paving and planter wall units installed on Bridge Street toward the Sunbridge Road junction.

 

Reminder: Temporary pedestrian crossings

Temporary pedestrian crossings have been opened across the city centre in places where works are happening.

Please note that the pedestrian route on the south side of Hall Ings has been temporarily diverted to the north side of Hall Ings to allow work on the new footway to continue between the junctions with Vicar Lane and Drake Street.

We have included a map of the pedestrian crossing points in the core of the city centre below. Please note that we have removed some crossing points on Bank Street, as they have been replaced with traffic-free open space. An extra crossing point has also been added on Bridge Street.

Map showing the pedestrian crossing points in the city centre. Crossings are in place at the following locations: Market Street, at the junctions with Charles Street, Bank Street and Bridge Street, as well as on Hall Ings at the junction with Bank Street.


Bridge Street Taxi ranks

Due to works happening in front of the main entrance to Bradford Interchange, the taxi ranks have been relocated to Drake Street and behind the Great Victoria Hotel.

There is temporary signage in place to direct people to the new ranks from their previous location.

If you have any questions about getting around the city centre, please do contact us via email at info@future-bradford.co.uk, or by calling our freephone information line at 0808 196 9119.

 
 

Reminder: temporary closure of the Bradford Interchange bus station 

Information about alternative bus stops for services unable to use the Interchange Bus Station can be found on the Metro website. You can read the Combined Authority's latest update on the closure of the Bradford Interchange Bus Station on their website

 

Find out more

You can find out more about the scheme on the Future Bradford website or by getting in touch using the details and links below. 

Get in touch if you would like to ask any questions

Email:info@future-bradford.co.uk

Write: Freepost BFD Highways

X (formerly Twitter):@bmdcHighways

Instagram:bradfordhighways

Facebook:Bradford Council Highways

 
 
 

Other news you might like


Previous
Previous

City Centre Construction Update 30 August 2024

Next
Next

City Centre Construction Update 16 August 2024